Covenants, Easements & Wayleaves: The Hidden Urban Interfaces Which Shape London Part 1

The Underground isn’t just defined by its infrastructure, but by its interfaces too. We look at the hidden world of asset interface management, and how it affects, and is affected by, urban railway management, and uncover more that can be achieved.

On the morning of 8 March 2013, a driver of a northbound main line railway service on the Northern City line between Moorgate and Finsbury Park noted the ingress of water into the tunnel. They communicated this to line control and the driver of the following train was instructed to proceed slowly and observe the situation. When he reached that point of the tunnel, he immediately stopped his train and, after reporting back, line control immediately halted all services between Moorgate and Drayton Park. The driver had spotted two augers that had pierced the tunnel.

Unexpected auguring of a problem. RAIB

This caused the suspension of services on this section of the line for several days.

The subsequent investigation of the event by the UK Railway Accident Investigation Branch (RAIB), identified that:

  • the northbound tunnel was located under private land;
  • the southbound tunnel was located under the adjacent main road;
  • boring was underway to provide piles for a new surface development;
  • 19 of the 39 proposed piles would have intersected the northbound Tube tunnel;
  • the longest piles would extend over 9 metres below rail level.

The subsequent report stated that the developer of the land above:

• did not appreciate the significance of an entry on the Land Registry Property Register (Cadastre);

• Searches undertaken on behalf of the client prior to it purchasing the site did not include Network Rail;

• A 1967 undertaking by the London Borough of Hackney, intended to give the tunnel owner the right to approve any proposed development, did not result in Network Rail being consulted before piling commenced;

• The structural engineer and contractors did not identify that an obstruction found in an exploratory borehole was part of a railway tunnel;

• Pre-construction documentary searches did not detect the presence of the tunnels or the need for additional searches;

• The planning approval process did not recognise the tunnel risk; Network Rail had no protection arrangements to identify risk due to proposed developments”.

RAIB Report: Penetration and obstruction of a tunnel between Old Street and Essex Road stations, London. 10 December 2014

Moreover, the report went on to state that Network Rail:

“relied on it being notified of proposed works, either directly by a developer or by a local planning authority after a planning application had been made, to protect its infrastructure. For this arrangement to work, it depended on third parties being aware of the presence of railway infrastructure including, as in this case, tunnels”.

Planned augering of 19 proposed piles. RAIB

The planned augering could well have been much more serious, as the above diagram shows. Had the augers pierced the tunnel at the wrong moment, they could even have drilled into a passing train, causing injury, derailment, and possibly death.

The complex world of interfaces

Despite the complexity of urban underground metro infrastructure and its interconnected relationship with its surrounding environment, there appears to have been little to no standardised scientific approach to analysing the way that railway infrastructure interfaces with its surrounding environment. This is perhaps because it requires a genuine multi-disciplinary approach: including legal, civil engineering, historical, geographical, transport, and urban planning considerations.

It is important to understand what the term interface means in this context. It is not about the boundaries between things, but the ways in which transport and urban infrastructure and its surrounding environment come together and affect each other.

The image below shows the physical interfaces between the railway infrastructure and its environment, of a building over a Metropolitan Line tunnel north of Farringdon. They consist of a retaining wall, supporting adjacent land and road, a tunnel under a building, and just visible in the right hand corner are girders forming part of a fly under for National Rail infrastructure (used by Thameslink):

Metropolitan Line tunnel north of Farringdon

The following image shows the corresponding property ownerships, colour-coded as follows:

  • red (A) London Underground land and airspace;
  • green (B) Network Rail land and airspace;
  • light blue (C) TfL Streets highway;
  • purple (D) local authority highway.
With property ownership overlaid. Nathan Darroch

Appreciating the interfaces

Palmer Street’s low building, opposite an entrance to St James’s Park station. Nathan Darroch

“Have you ever considered why this is a one-storey building?”

The question is asked of us by Dr Nathan Darroch, formerly a Land and Vesting Engineer at London Underground, now Research Fellow at the University of Aberdeen, and part time Lecturer within the Schools of Engineering and Civil Engineering and the Built Environment at London South Bank University.

The building in question is a cafe on Palmer Street. It is a one storey building, surrounded by others that are not.

“Until the 1920s,” he continues, “St James’s Park station sat within an open cutting with a roof, similar to other sub-surface stations on the western end of the District and Circle lines.”

“Eventually, however, rising car ownership meant an increasing demand for car parking space in central London, including among directors of London Underground – then the LER [London Electric Railway Company] – working at 55 Broadway, just across the road. Due to limited opportunities for land ownership nearby, LER were forced to think creatively. So they built their car park on the only strip of available land, and airspace, they owned: above the narrow railway cutting.”

It is this, Darroch explains, that accounts for the single storey cafe building today. Whilst the usage may have changed, but the interfaces have not. The building takes its support from the old retaining walls forming the cutting. This is an interface that is over 100 years old, but still in use today.

Palmer Street’s infrastructure cross-section. Nathan Darroch

Indeed, the supporting structure for the building is clearly identifiable from the Victoria end of the westbound platform. As are the different natures of construction for the Palmer Street overbridge constructed with the railway around 1865 to accommodate the existing road (required by law); the office buildings forming part of the 55 Broadway complex; and 55 Broadway, itself (constructed in the late 1920s), and the building above the western St James’s Park station entrance, constructed in the 1980s. All interfaces, completed across many decades.

“London is not the only urban interface to have these interfaces.” Darroch says. “But its history does make the complexity of unpicking them interesting. This city has been excavated, developed, tunnelled, bombed, and redeveloped for centuries. And there are so many other contractual issues that greatly complicate construction, repair, maintenance, and redevelopment besides.”

Land acquisition and management

As Darroch explains, some of this dates right back to the way in which the Underground, as we know it today, was legally created. By 1845, the UK was experiencing a railway mania. The legislation for authorizing railway construction was based on centuries old principles dating back to the Roman era, including responsibilities for bridges and land acquisition, which had later been adapted for canal construction.

“The construction of railways saw the adoption of similar principles of land acquisition seen in the construction of roads, bridges, and canals, but these were based on the interpretation of lawyers within the Houses of Parliament, rather than a standardized procedure.” Darroch adds.

“This was remedied with the passing of the Land Clauses Consolidation Act 1845 (LCCA) and the Railway Clauses Consolidation Act 1845. But these still needed refinement. This happened in 1863, when they were both amended. These laws are still in force today.”

The London Underground, however, was different. Its unique sub-surface nature required specific legislation of its own at the time, and this legislation incorporated many of the original principles of the 1845 LCCA.

“Main line railways had to sell their surplus lands within 10 years of their opening,” Darroch offers, by way of an example, “the underground railways could retain ownership of the land for as long as they wished.”

The sub-surface railways, which are generally between 0.2 and 5m below ground level, had basic statutory rights and obligations to acquire land by:

  • the right to use the subsoil under a road;
  • the ability to compulsorily purchase the whole or part of land and buildings (mostly basements and cellars); and
  • the ability to buy an easement under private land and buildings.

This had the effect of half of the Circle line being constructed across, not exclusively under, the street pattern, resulting in the demolition of buildings, construction of road bridges over the railway, and the employment of open cuttings within an already densely developed urban environment.

Ray Street Bridge, north of Farringdon station. Bing Maps, 2020.

Some of those cuttings are now covered over to form covered ways with buildings located above, with the introduction of electric trains from 1904. The remaining half of the Circle line is actually under roads, public open space (parks), or within land that forms stations.

Changing the model yet again

By the 1930s, the underground railways were permitted to ‘take’ the subsoil and land they required for the construction and presence of their infrastructure. This enabled the Tube railways to cut across street patterns for more considerable distances without having to buy an easement or land. Compensation was only paid for loss of land or sub-soil where there was an adverse effect on existing or proposed urban development, where this was already proposed at the time of the railways construction. This principle was introduced as the sub-soil was considered worthless to the majority of property owners as they had no use for it

As with the thinking for the early Tube railways being allowed to purchase easements under property, this change had little effect on property development at that time, due to the low height and depth of buildings. The main effect of this new railway was at line interchange station sites, where existing stations were increased in size and capacity below ground, as:

  • this could affect the presence of existing buildings, and
  • as well as affecting the presence, property, and protection interfaces between the railway and those buildings.

Kingsgate House development, Victoria Street, Westminster

A recent example of effective collaboration between an adjacent land owner/developer and the underground railway owner was the Kingsgate House development on Victoria Street, central London. In this instance, the original building, directly adjacent to the District and Circle lines, was entirely demolished and a new development consisting of eight storeys below ground level, as well as foundations to support 14 storeys above ground level, were erected.

Just how problematic this situation could have been is highlighted by the images below, which show the basement excavation and the property ownerships at the site in question:

Kingsgate Development, Victoria Street
Ownership overlay. Nathan Darroch

where:

  • red, labelled A – land, airspace and subsoil owned by London Underground;
  • blue, labelled B – land, airspace, and subsoil owned by the developer;
  • green, labelled C – land, airspace, and subsoil owned by an interfacing stakeholder to London Underground;
  • blue hatched with red, labelled D – land, airspace, and subsoil owned by B; within which London Underground has an easement for the presence of its tunnel;

Without London Underground’s input, the risks to the railway would have been high, both to its infrastructure, and as the auger incident demonstrated, to passenger safety and service levels. However, with London Underground’s input, there was no adverse disruption to the railway, its assets, services, or passengers, and the new development was completed safely.

The arc of a covenant

So far, so complex. But it gets worse. Where the sub-surface railways had purchased land that was surplus to their requirements, they could sell or lease it for urban development. Within the sale or lease, they also had the opportunity to impose protection for their infrastructure in the form of covenants. This is a contractual requirement, mostly to consult and gain the explicit consent of the transport infrastructure owner, before carrying out any work on the land (eg demolition, building extensions at roof, ground, or below ground, etc).

New techniques bring new laws

If every piece of the covered Underground involved an active covenant, then managing its interfaces would be considerably easier. However, land was not always purchased, meaning that covenants could not always be imposed.

This became even more common as tunnelling and electrification technologies advanced. This meant deeper railways which were anticipated to have a considerably lesser effect on their surrounding environment. As a result, changes to land acquisition were incorporated within the authorizing legislation for Tube railways.

“This included the ability to only buy an easement under private property, or to use the subsoil under public highways free of subsoil purchase costs.” Darroch explains, “Indeed the latter became the option of choice for much of the expansion between 1890 and 1907, to save having to pay sometimes extortionate prices.”

“For example, to go under the warehouses near London Bridge, the builders of what is now the Northern line had to pay £3,000 for an easement of fifty to sixty yards. That’s about 2% of the property’s rateable value of about £150,000.”

“Mitigating the need for incursion under private property, often by locating one Tube tunnel above another under the road, became a common feature of future lines.”

Westminster Station. Note Jubilee Line stacked tunnels under the road. Nathan Darroch

Maintaining the tunnels under roads, however, has had an adverse effect on today’s network, where services are limited by the tight curvature of the tunnel alignments. For example, the Bakerloo line between Charing Cross and Oxford Circus stations follows the roads above, including 90 degree turns in the tunnels, which impose very low speed restrictions to this day.

Foundations go deeper

Where the subsoil was acquired through an easement, the railway had no ownership of that subsoil. In effect, what was granted was simply a right to pass through it. Given the depth of much of the Tube network, this was not really seen as an issue in the first half of the twentieth century, but it has serious implications now.”

“Up to the 1950s, most buildings had only one or two basement levels and shallow foundations.” Darroch explains. “Since then, however, buildings have become ever taller, requiring considerably deeper piled foundations.”

“This has led to increased potential presence, property, and protection interfaces between the underground railway infrastructure and its surface environment, through potential conflicts between the use of the subsoil for transport and urban infrastructure.”

Here is one of Darroch’s presentations that shows the complexity and extent with a number of asset infrastructure interface examples.

How can we better know what is underground?

The infrastructure impingement example noted at the start of this piece shows that modern London, indeed every major city, is becoming too complex to rely on individual professionals, or professions, to ensure critical knowledge of infrastructure location and ownership.

As a result, what was really required was the development of a new discipline to deal with the complexity of identifying, classifying, and storing such data, so that a process could be established to make it much easier to check for any issues.

In the next part, we delve into more detail of Tube and Metro tunnel infrastructure interface issues. These principles still apply today for new underground railway infrastructure, such as Crossrail.


19 comments

  1. Great read Nathan. Really needed too. This is certainly the sort of thing I love Reconnections for.

    I’m reminded – as I often are – to a Douglas Adams quote

    “We all like to congregate at boundary conditions. Where land meets water. Where earth meets air. Where bodies meet mind. Where space meets time. We like to be on one side, and look at the other.”

  2. Interesting article, having previously idly read the RAIB report on the auger incident!

    The suspect the Westminster image caption should refer to the Jubilee line – diverting the Victoria line to that station would have been very convenient for my morning commute, back when that was a thing! [Corrected, cheers. LBM]

  3. Fascinating, looking forward to more.
    There have been ( IIRC ) two similar breaches of the Cental Line, by uninformed peple with Auger drills, including one that actually pierced the roof of a moving train, fortunately without killing anyone.
    At the moment, I can’t find the references, so perhaps someone might oblige?

    There was also the recent “absence of an interface” at Wimbledon, wasn’t there, where a very short section of track “Belonged to Nobody” & so was not maintained, leading to a derailment …..

  4. This may be of interest, amazing tools out there although obviously depends on finding the information and understanding how reliable it is. I think this enables you to rate the reliability to give a score for certainty.

    This presentation uses Crossrail 2 as the underground infrastructure planning example.

  5. Hello Greg and Underground Mole, thank you for your comments (Brian and Nathan, too!).

    Here is the link to the Wimbledon RAIB incident.
    https://www.gov.uk/government/publications/safety-digest-012018-wimbledon/derailment-of-a-passenger-train-near-wimbledon-south-west-london-6-november-2017

    With regard to Underground Mole’s observation, the matter of ensuring stakeholders generate and have access to evidence-based data for the interfaces, is the next part of the story 😁

  6. Fascinating stuff this. Love it.

    A couple of proofing points:
    – In the para starting “The image below shows…” it’s not clear what the mention of the “right hand corner” refers to as the Thameslink dive-under is clearly to the left of the picture. Also strictly the infrastructure owner is “Network Rail” and not “National Rail”.
    – It’s not clear whether the cafe and/or car park at St James’ Park described in the text is the same as “Palmer Street’s low building” and whether this was built in the 1920s or the 1980s, is this a reference to one building or two?
    – the key to the A/B/C/D picture of Kingsgate Development lists A twice and lists B & D as the same thing. Also there is only one “hatched” area in the image.

    As a matter of interest I’m curious if anyone thinks the Moorgate line incursion would have happened had the tunnel been a London Underground tunnel rather than a Network Rail tunnel?
    I do recall seeing planning “constraints” listed on a London Borough planning map which included the exact routes of LU tunnels. It’s baffling to me that developers, architects and borough planners would not have seen these as I came across them just doing basic planning research for a modest home extension – so maybe the Northern City Line is missing from this sort of documentation due to the NR ownership?

  7. Paul
    I remember from the time of the Old Street Auger Incident, that the developers actually did a very quick, amateurish check & found there were “No Underground tunnels” & therefore it was automatically safe to bore holes … Um.
    The piercing of the Central Line tunnel ( some time 1980 – 1995 ?? ) should have thus been prevented – it’s very annoying that I can’t find references to that incident.

  8. Articles such as this are welcome, and I am looking forward to subsequent parts. One aspect of the LU I am hoping that will be touched on at some point in the future is the electrical infrastructure that supports the tube lines, and if it is of the same era of technology that employed rotary converters and mercury arc rectifiers as seen on some of the legacy lines of the subways here in the US.

  9. Greg T …. like you I can’t find details of the Central line incident , but recall that it happened circa 1980, based on when the vehicle was being repaired. This incident led to the formation of a small team whose role was to actively monitor planning applications. They also travelled routinely on the open sections of line looking for construction activity adjacent to the railway and walked the line of route for tunneled sections with the same objective. Finally they work with those who want to construct things adjacent to or over the railway to ensure that the work is done safely. The team was called Infrastructure protection. As far as I know, this team still exists.

  10. Update
    It seems to hav happened twice, actually.
    A minor, but could-have -been worse incident in 2016 … Link here
    And a very scary, amazingly “lucky” near miss .
    Unfortunately all I can find (for now) is a facebook page.
    Link here for that one
    That no-one was even injured, is remarkable.

  11. @ Greg T: the incident you’re looking for is being referred to in the Old Street RAIB investigation:

    “A 200 mm diameter drill penetrated the roof of a Central Line tunnel near Wanstead on 4 March 1986 when test borings were taking place for the M11 link road at Leytonstone Green Man roundabout. This incident caused damage to two trains and minor injuries to the driver of the first train.”

  12. There is an interesting, fairly recent version of tube lines following the roads. The Jubilee line runs directly under the main line viaduct between Southwark and Bermondsey, save for where it takes a “short cut” at Borough Market to avoid the sharp curves followed by the viaduct. The BR engineers were not too happy about this and there was extensive monitoring of the viaduct while and after the tunnels were bored, but it meant that the line could be built with just one easement covering several miles.

  13. Going back into history, this was one of the principal reasons for the existence of & business conducted by The Railway Clearing House.
    The “Railway Juction Diagrams” were a very visible manifestation of that careful demarcation of who owned what & exactly where the ownership boundaries lay. And which were then used for calcualting rates & similar payments for use of Running Powers over other companies lines.
    Even when said Railway company had no locomotives, such as the CLC, or even rolling stock, like the Forth Bridge Railway company.

  14. Great article, the interface with London’s rivers is also a fascinating subject, right from the beginning with the new tunnel under the Thames flooding and Brunel’s lucky escape.

  15. @Paul

    To respond to your queries in order:

    a.i) Correct to ‘left hand corner’
    ii) Corrected to ‘Network Rail’
    b. The cafe and car park are the same as “Palmer Street’s low building”, and it was built in the 1920s.
    c. The Legend/Key for the Kingsgate Development has been updated.

    LBM

  16. Nice. Some observations:

    a) LUL/TfL has all sorts of weird bits of land for schemes not completed. Such as: a) Bouverie Street – the vent shaft for Phase II of the Fleet/Jubilee Land. Not to mention the trial tunnel at New Cross….

    b) Land Ownership is utterly weird. Such as:
    i) Marble Arch station is a flying freehold.
    ii) Crossrail under the Royal Park isn’t a freehold
    iii) Westminster Station was originally TfL/LU freehold – 999 year lease to Parliament. Flipped a few years ago to simplify things….

Comments are closed.