How might we shape the pattern of London’s growth and development to help bring about a more sustainable outcome? In this part (and the next) of our continuing series we’ll look at the ‘quantity and quality’ schemes arriving at this electronic platform now for rail (above ground and below), surface transport and integration and interchange.
Because there’s a lot to say, we’ll focus first on the overall shape of what’s offered, and particularly on the National Rail element within London and the Home Counties.
The story so far
Part 1 set out the context for the proposed London Infrastructure Plan 2050 (‘London 2050’). It is founded on foreseen growth in population and jobs, and has the goal of ensuring that London maintains a pre-eminent status at a World City level in the decades to come with better capacity, better reach and better quality of lives. We saw that the consultation document has three outputs: a policy case, a manifesto and a funding bid. The requirements for large scale expansion of funding were described, including the transport networks. It was noted that London has been offered less freedom of planning choice than one might have desired, because of how the modelling has been undertaken.
Part 2 expanded the topic of forecasting, and showed how this influenced the spatial and transport choices for London. We discussed some key topics:
- agglomeration theory and practice for the principal London jobs locations
- population densification and dispersal options, including beyond Greater London
- the politics of a growing London
- impact of current London airport planning
- future options for outer London, and the merits or not of the proposed Outer Orbital railway
- some quality and equality issues.
Limited timescale to deliver new capacity
We can now review, also in context, the transport schemes which individually and jointly are brought forwards in London 2050 – and those which appear absent from such advocacy.
London 2050’s Transport Support Paper (TSP) has set out a long list of possible projects. These are costed at a nominal level of detail, and are set out in TSP pages 129-164 for rail schemes (we’ll cover road and other transport schemes in due course). It is interesting that these rail-based projects are sorted by mode, not by project development phase, overall timescale, affordability, wider benefits, nor relative capacity impacts.
So this is not a prioritised list in the sequence in which it is published, although such measures are set out in the TSP tables. The bulk of existing thinking already takes us to the 2030s or beyond. To look as far as 2050, there has been much behind-the-scenes analysis to consider a mix of options that could help to deliver London’s capacity requirements. As we shall see, even that may not have gone far enough, though the forecasting points towards more of the same.
While there will be a need for some new lines, the larger task will be to expand, operate and maintain the rail capacity on existing lines, in order to accommodate the demand volumes. The funding needs, engineering and operational challenges, and pressures on project management, available workforce and skills, are far greater than ‘more of the same’.
Two simple numbers make this point: according to London 2050: “given the limited scope for London’s roads to provide additional capacity, demand on the Underground and rail is likely to go up by 60 and 80 per cent respectively” (London 2050 consultation document, page 9). That’s over the next 35 years, compared to the 183 years it has taken until now to develop the network since planning began for the London and Greenwich Railway in 1831. It will take strong policy, political and funding prioritisation, to deal with this tall order!
In volume, the actual numbers that might be foreseen are suggested below, on a route by route basis. These are not set out within London 2050 itself, but from available transport industry planning documents. We start with the National Rail services. As we shall see, these are already largely forecast through to 2050 and beyond, though whether there is adequate capacity is another matter, and whether London 2050 anticipates those requirements appropriately, with outline funding identified, another matter still.
You can’t buck the system
The Hunting of the Snark is sometimes a useful aide-memoire. “Other maps are such shapes, with their islands and capes! But we’ve got our brave Captain to thank: (So the crew would protest) “that he’s bought us the best– A perfect and absolute blank!”
That’s great if you want to maximise your options. The problem is that a blank is the one thing London’s spatial and transport geography isn’t, and doesn’t permit for future projects. Its past will shape its future. Already detailed Network Rail planning is under way on the main lines for the 2020s, up to the fourth quinquennial period set out in London 2050’s costings, towards 2030.
Control Period 7 (CP7), if it exists in the future under Treasury control of Network Rail, will end in 2029. That’s roundly the date in a nice world when:
- Crossrail 2 and HS2 Phase 2 are being tested pre-opening
- the first of the New Tubes for London – the Piccadilly Line – has been working perfectly since 2027 (according to the latest TfL re-spec)
- all of Network Rail’s 2011 London & South East Route Utilisation Strategy proposals, and some more recent scheme thinking, have been implemented to achieve adequate capacity by 2031.
How hopeful are we about all that?
As for Control Periods 8 to 11, on to 2049 (only one year short of 2050), Network Rail last year in its Long Term Planning Process (LTPP) market analyses set out expectations about foreseeable 30 year changes to demand volumes for the period 2013 to 2043, on the main rail corridors. There is a specific strategy for the London & South East catchment (actually London and Home Counties).
So it isn’t a huge jump for the main line rail sector to have prognostications about 2050, compared to 2043, even if the rate of demand will have to be revised for jobs and population. Just one more Control Period and a bit. So it can be 2043 plus or minus some variation – providing that a similar economic geography is anticipated.
Network Rail already has some 2050+ forecasts!
We’ve shown that, whether you like it or not, the forecasting processes are largely geared towards more of the same, at least for jobs – additional radial-centric commuting. This is driven by a location fix for the bulk of additional jobs, to be ‘agglomerated’ densely in versions of the existing Central Activity Zone, plus options for one or more of: (a) higher CAZ density; (b) an expanded CAZ into the present City Fringe; (c) support for the CAZ plus Satellite Activity Zones, with SAZ indicated at Canary Wharf, Stratford and Old Oak Common.
The 2011 London and South East Route Utilisation Strategy (LSE RUS) forecast growth from 2011 to 2031. Some route-specific changes were also included, having their main impact before 2023, such as Crossrail 1 and Thameslink.
The LSE RUS used a similar growth factor from 2011 to 2023, 0.86% commuting growth per annum, as is used by the 2013 to 2043 LTPP, for the same period. This is noted in the LTPP document:
For all four [LTPP] scenarios the level of growth in central and inner London employment over the first 10 years of the forecasts was kept at the rate used in the London and South East RUS. This growth rate of 0.86 per cent per annum was taken from the London Plan 2011.
Like the LSE RUS, the LTPP adopted the GLA’s 2031 forecast in the 2011 London Plan, of 1.3 million additional population from 2007 to 2031, and 750,000 additional jobs over the same period. Where the LTPP diverged from the RUS, was to vary the forecast beyond 2023, with variable 20 year population and jobs projections to 2043.
There were four scenarios taken forward in the LTPP, varying from ‘Prospering in Global Stability’ (PGS) to ‘Prospering in Isolation’ (PII), ‘Struggling in Global Turmoil’ (SGT), and ‘Struggling in Isolation’ (SII). Only PGS and PII compare closely with the general London 2050 scenario, while PGS is closer in function and style. [See LTPP Chapter 6, pages 25-43]
In PGS, London is the first and principal point of interaction between a prospering UK economy and foreign economies. London and Home Counties area employment growth is forecast there at 0.88% per annum beyond 2023 to 2043, a compound 32.0% increase on 2011. This is lower in PII, where strong UK economic growth is driven by burgeoning domestic production located outside of large city centres, and London and Home Counties employment growth after 2023 is forecast at 0.67% per annum, compound 26.7% from 2011. SGT is 15.8%, SII 14.7%.
In contrast, London 2050 looks at a compound 28.6% jobs increase in its central projection, an average 0.65% per annum overall increase in employment from 2011.
What this all means for London 2050 planning, is that Network Rail’s existing 2043 maximum demand forecasts (which exclude the effects of HS2) are broadly the equivalent of London 2050’s rail requirements projected to 2047-48 (PII) or 2054 (PGS). So we already have some London 2050 route-by-route estimates, for London’s main lines. We shall assume in this discussion that PGS applies, as these are the maximum capacity demand figures already published for 2043 and we are looking at known data.
The distribution of additional jobs is foreseen in London 2050 as follows:
If trends continue, the professional, real estate, scientific and technical activities sectors are expected to see the largest increase in employment over this period (nearly doubling to 1.4 million). Two thirds of the total increase in jobs are expected to occur in the Inner London boroughs.
This points once again to increased, heavy reliance on rail travel to and within Inner and Central London, including radial and orbital flows and large-scale passenger distribution from termini.
Sequence of discussion
The sequence adopted for the rest of this article is therefore:
- Tabulation of what the 2011 LSE RUS saw in terms of capacity gaps by 2031 if nothing new was done other than existing committed schemes.
- New tabulation including the 2043 LTPP forecasting for PGS volumes, and contrasting this against the same 2031 capacity gaps as a starting point – so this represents a nominal commute-to-jobs equivalent of a ‘London 2050+’ forecast demand versus a baseline 2031 capacity supply.
- A summary of LSE RUS comments about how that report sought to fill the pre-2031 capacity gaps (generally with positive results), plus a summary by this author about what the foreseeable additional gaps between 2031 and 2050+ mean, and possible ways of addressing those.
- Review what extra schemes London 2050 proposes to bring to the National Rail party, and whether they alleviate the foreseeable 2050+ capacity gaps.
- Round-up of National Rail and London 2050, and related topics otherwise left hanging.
What the 2011 LSE RUS estimated, for 2031
Merging the LSE RUS and LTPP estimates of projected demand flows (and taking PGS as the upper limit), shows below, in the next two tables, the following gaps in demand and supply on London’s National Rail corridors in 2031, and in 2050+. We should bear in mind that these are forecasts made a long way ahead of any out-turn results.
The table below shows peak hour commuting capacity gaps on London’s main lines in 2031, as set out in 2011 LSE RUS, without the RUS’s subsequent proposals for intervention and relief (nb: This is for the busiest single hour, not for the more usual 3 hour AM peak period)
2031 morning peak busiest hour, from LSE RUS 2011
Demand, capacity, route utilisation and gap forecasts (do-minimum)
Key: Numbers in red are those where demand exceeds capacity. Numbers in green are estimates of Main Orbital 2010 based on 480 per train, 160 seated, except GOBLIN. Includes 1 tph Southern on WLL in AM peak. (*) indicates different annual basis.
2031 Capacity: Base Line changes | Live estimate from RUS data | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
2010 busiest AM peak hour volume | 2031 Capacity + Demand high peak hr, Capacity LSE RUS Ch.5, Demand Ch. 6 | |||||||||||
Route into / Service group | 2010 Seated Capacity | 2010 Standing Capacity | 2010 Seats + Standing Capacity | 2010 Actual Demand | 2011 Actual Demand | 2031 Seated Capacity | 2031 Standing Capacity | 2031 Seats + Standing Capacity Anticipated | 2031 Demand (Forecast) | Demand / Capacity Utilisation Ratio 2031 | Forecast Gap 2031 (Based on 85% utilisation) | |
Total Passenger volumes | 238,160 | 100,270 | 338,430 | 298,200 | 304,700 | 282,850 | 183,750 | 466,600 | 410,800 | 88.0% | 14,190 | |
London Paddington | RBIR | 95.8% | 42,795 | |||||||||
Crossrail GW route | n/a | n/a | n/a | n/a | n/a | 7,800 | 9,800 | 17,600 | 12,800 | 72.7% | 0 | |
Relief line trains (excluding Crossrail) | 2,500 | 600 | 3,100 | 4,100 | 4,100 | |||||||
Heathrow Express | 2,800 | 0 | 2,800 | 800 | 800 | 2,800 | 0 | 2,800 | 1,300 | 46.4% | 0 | |
Main line + other fast trains | 8,000 | 300 | 8,300 | 9,000 | 8,500 | 8,600 | 600 | 9,200 | 13,600 | 147.8% | 5,780 | |
London Marylebone | ||||||||||||
All Services | 5,700 | 1,000 | 6,700 | 6,100 | 6,500 | 6,500 | 1,300 | 7,800 | 7,800 | 100.0% | 1,170 | |
London Euston | ||||||||||||
HS2 services | ||||||||||||
Long Distance | 5,800 | 0 | 5,800 | 3,700 | 3,300 | 6,900 | 0 | 6,900 | 6,500 | 94.2% | 635 | |
Suburban | 7,600 | 3,000 | 10,600 | 8,100 | 8,800 | 8,100 | 3,300 | 11,400 | 12,100 | 106.1% | 2,410 | |
London St Pancras | ||||||||||||
International services | ||||||||||||
High Speed 1 (domestic) | 4,200 | 1,500 | 5,700 | 2,500 | 2,500 | 4,200 | 1,500 | 5,700 | 5,300 | 93.0% | 455 | |
MML Long Distance | 2,900 | 0 | 2,900 | 2,300 | 2,500 | 2,900 | 0 | 2,900 | 3,800 | 131.0% | 1,335 | |
Thameslink MML | 8,500 | 3,200 | 11,700 | 9,900 | 9,700 | 8,700 | 15,800 | 24,500 | 14,700 | 60.0% | 0 | |
London Kings Cross | ||||||||||||
Thameslink ECML | n/a | n/a | n/a | n/a | n/a | 4,100 | 7,600 | 11,700 | 13,000 | 79.8% | Gap on Camb / Pboro. Most WGC to Tlink | 1,500 |
Great Northern | 8,000 | 1,800 | 9,800 | 7,900 | 16,700 | 4000 | 600 | 4,600 | ||||
Hertford-Moorgate | 3,700 | 1,400 | 5,100 | 7,900 | 4,700 | 1,700 | 6,400 | 8000 | 103.9% | 1,455 | ||
Welwyn Garden City-Moorgate | 1,900 | 700 | 2,600 | 900 | 400 | 900 | 400 | 1,300 | ||||
ECML Long Distance | 2,700 | 0 | 2,700 | 2,000 | 2,600 | 4,900 | 0 | 4,900 | 3,000 | 61.2% | 0 | |
London Liverpool Street | ||||||||||||
West Anglia incl Main Line | 11,400 | 4,400 | 15,800 | 14,300 | 15,700 | 13,500 | 5,000 | 18,500 | 18,000 | 97.3% | 2,275 | |
Great Eastern Main Line | 16,700 | 2,200 | 18,900 | 16,500 | 19,500 | 18,600 | 4,300 | 22,900 | 24,600 | 107.4% | 5,135 | |
GE Inners | 8,900 | 3,200 | 12,100 | 12,900 | 13,600 | 3,800 | 1,400 | 5,200 | 21,000 | 90.1% | 01 | |
Crossrail GE route | n/a | n/a | n/a | n/a | n/a | 7,100 | 11,000 | 18,100 | ||||
Crossrail Abbey Wood route | n/a | n/a | n/a | n/a | n/a | 7,100 | 11,000 | 18,100 | 11,900 | 65.7% | 0 | |
London Fenchurch Street | ||||||||||||
All services | 12,100 | 4,100 | 16,200 | 15,300 | 16,300 | 14,900 | 5,200 | 20,100 | 17,000 | 84.6% | 0 | |
To / Via London Bridge | ||||||||||||
Terminating Sth. London (inners) | 7,100 | 3,300 | 10,400 | 9,200 | 9,300 | 9,800 | 3,500 | 13,300 | 11,500 | 86.5% | 195 | |
Terminating (fasts via E.Croydon) | 8,600 | 4,400 | 13,000 | 13,300 | 15,200 | 7,800 | 14,200 | 22,000 | 24,400 | 86.8% | 515 | |
Thameslink Sussex | n/a | n/a | n/a | n/a | n/a | 4,100 | 2,000 | 6,100 | ||||
London Charing X/Waterloo East | 19,200 | 10,600 | 29,800 | 26,200 | 60,500 | 19,200 | 10,600 | 29,800 | 50,900 | 80.5% | 10002 | |
London Cannon Street | 15,500 | 9,000 | 24,500 | 20,900 | 16,800 | 9,700 | 26,500 | |||||
Thameslink Kent | n/a | n/a | n/a | n/a | 2,500 | 4,400 | 6,900 | |||||
London Victoria | ||||||||||||
Kent routes | 9,500 | 2,300 | 11,800 | 10,300 | (inc above) | 8,400 | 4,100 | 12,500 | 8,700 | 69.6% | 0 | |
Fast trains via East Croydon | 11,800 | 4,900 | 16,700 | 14,200 | 12,100 | 12,900 | 5,700 | 18,600 | 19,500 | 104.8% | 3,690 | |
Stopping trains via Balham | 7,100 | 3,200 | 10,300 | 9,700 | 12,900 | 11,500 | 3,700 | 15,200 | 10,300 | 67.8% | 0 | |
London Blackfriars | ||||||||||||
Thameslink | 8,000 | 2,700 | 10,700 | 10,400 | 10,900 | 2,500 | 4,800 | 7,300 | 11,900 | 84.4% | 9003 | |
Terminating (all services) | n/a | n/a | n/a | n/a | n/a | 5,400 | 1,400 | 6,800 | ||||
London Waterloo | ||||||||||||
Windsor Lines (all services) | 7,800 | 8,400 | 16,200 | 13,600 | 13,300 | 9,000 | 10,300 | 19,300 | 17,100 | 88.6% | 695 | |
Stopping trains via Wimbledon | 13,000 | 16,200 | 29,200 | 22,700 | 23,600 | 15,100 | 19,600 | 34,700 | 25,500 | 73.5% | 0 | |
South West Main Line | 13,400 | 0 | 13,400 | 14,800 | 15,800 | 13,400 | 0 | 13,400 | 18,300 | 136.6% | 6,910 | |
Main Orbital Routes | ||||||||||||
West London Line | 940 | 1,430 | 2,370 | 2,700 | * | 900 | 2,100 | 3,000 | 5,500 | 183.3% | 2,950 | |
East London Line | 1,920 | 3,840 | 5,760 | 4,200 | * | 2,370 | 4,730 | 7,100 | 9,800 | 138.0% | 3,765 | |
North London Line | 1,168 | 2,336 | 3,504 | 2,700 | * | 1,080 | 2,420 | 3,500 | 3,000 | 85.7% | 25 |
185% not used for CR1
2+20min stand
3gap via H.Hill
The 2011 LSE RUS projected a 43,000 passenger capacity gap overall, on the London’s main line routes in 2031, starting with a 2010 demand baseline. This assumed that no major investments were undertaken beyond those committed then (which included Crossrail and Thameslink). Every route needed some lesser or greater intervention to deliver the expected capacity requirement in 2031.
This was for the busiest morning peak hour (taken by the RUS as 08:00 to 08:59, though 08:15 to 09:14 can be busier). The RUS ignored 07:00-07:59, and 09:00-09:59, as infrastructure investments required for the busiest hour should accommodate demands in the other hours. This may be true for infrastructure but might not be so for train numbers, as extra trains are likely to be required for additional inbound travel in those periods as well. An estimate of a full 3 hour AM peak period in 2031 might be over 0.9 million inbound passengers on National Rail, if taking the busiest hour as 45% of 3 hours.
The LSE RUS thought that delivering this additional capacity was possible in most cases, for example with investment in Bow-Stratford capacity to assist the Great Eastern Main Line. Other solutions are required elsewhere. West Coast main line commuting relies on HS2 and Crossrail-WCML, in order to free up enough train slots. The Great Western main line needs Crossrail extension to Reading and diversion of Heathrow Express onto the relief lines as a Crossrail Express, to free up enough capacity by 2031 between London and Reading on the fast lines. The latter opens up a complex commercial debate between Heathrow Airport, Network Rail, Department for Transport and the Office of Rail Regulation (ORR), because of track ownership and slot allocation issues.
There is still no complete solution offered in the LSE RUS for the South Western mainline long distance and outer suburban commuting growth. Options there are a fifth track into Waterloo from Surbiton (far from easy) or a revised Crossrail 2 coming the other way from Central London, to take away some inner suburban flows and allow some slots to be used by longer distance trains. Even so full relief is not guaranteed. Crossrail 2 was also likely to be useful for West Anglia in due course. Longer trains and platforms were a common medicine, and the main solution for London Overground.
What the 2013 LTPP estimated, for 2043
In planning for London 2050 main line capacity, it might be theoretically possible to regard 2031 as giving the ability to restart planning with a zero capacity gap (but not on SWML). However there will be a busier baseline railway, having little or no extra capacity available using conventional methods of capacity relief, because getting to 2031 will have used up most of the margins. It also assumes that all supplementary LSE RUS investment requirements have been authorised and completed, which might be optimistic.
Worse, Network Rail’s LTPP assumes a wider spread of population than London 2050 is discussing, with comparable growth across the whole London & Home Counties area, but is similar to London 2050 on jobs. London 2050 has a high population within the GLA area. So pressures on inner suburban services with this maximum growth may be greater than projected, already by 2031 and much more so by 2050.
Whilst in theory those extra inner passengers might require fewer extra trains than outer commuters, because of permitted inner standee levels, this may not correlate with available inner train slots on allocated tracks. Meanwhile Network Rail’s outer commuter forecasting might still hold true, for example if higher value jobs exceed expectations, so resulting in a worse net capacity gap than shown below!
Alternatively, as London 2050 shows in its modelling options, move a million of the forecast population outside London, and outer suburban commuting pressures then grow bigger, faster, sooner than Network Rail’s PGS (Prospering in Global Stability). You also need more train paths for outer suburban commuters, because of the standee proportions mandated on inners but not outers.
Overall, Network Rail’s forecast growth in outer suburban commuting gives no comfort that in any scenario there will be fast tracks with spare capacity for relieving inner area crowding.
The London 2050 (mainline capacity) table is derived directly from the Network Rail LSE RUS and LTPP data. An 85% route capacity utilisation is used, as in 2031 estimates, as a ‘safe maximum’ for workable flows. The LTPP 2043 maximum growth scenario for jobs is taken as equivalent to London 2050+, on the jobs estimates described above, though without potential extra inner suburban volume caused there by greater population).
Below are the peak hour commuting capacity gaps on London’s main lines in 2050+, based on Network Rail 2043 projections – similar to London 2050 jobs growth taken to 2054. No interventions beyond LSE RUS 2031 baseline, so adds to the 2031 gaps:
2060 morning peak busiest hour, from LSE RUS 2011 and LTPP 2013, using PGS (Prospering in Global Stability) as the growth rate
Demand, capacity, route utilisation and gap forecasts (do-minimum)
Key: Orange numbers are those where there is any standing on Outers. Red numbers are those where there is standing on Inners, including Crossrail. Italics are used where the 2043 demand is not stated in LTPP and has been estimated by taking the LSE RUS 2031 reduced to 2023, then growth at PGS rate 2023 to 2043.
LTPP 2043 = 2060 demand | Straight line growth, 2023 > 2043, LTPP PGS basis = London 2060 | |||||
---|---|---|---|---|---|---|
Route Into / Service group | PGS basis, as direct input from LTPP figures |
2060 demand 2031 capacity utilisation ratio |
2031 base Seats | Left standing in 2060 if 2031 base seats |
% passengers standing in 2060 over 2031 base |
Forecast gap 2060 (85% use, 2031 base capacity) |
utilisation ratio average > |
516,275 | 110.6% | 283,168 | 233,107 | 45% | 119,665 |
utilisation ratio, route basis > |
117.6% | <implied ratio> | 242,719 | 47% | 129,277 | |
London Paddington | ||||||
Crossrail GW route | 16,500 | 80.9% | 10,600 | 5,900 | 36% | 0 |
Relief line trains (excl Crossrail) | ||||||
Heathrow Express | ||||||
Main line + other fast trains | 17,000 | 184.8% | 8,600 | 8,400 | 49% | 9,180 |
London Marylebone | ||||||
All services | 11,400 | 146.2% | 6,500 | 4,900 | 43% | 4,770 |
London Euston | ||||||
HS2 services | not in LSE RUS or LTPP | |||||
Long Distance | 7,100 | 102.9% | 6,900 | 200 | 3% | 1,235 |
Suburban | 16,600 | 145.6% | 8,100 | 8,500 | 51% | 6,910 |
London St Pancras | ||||||
International services | not in LSE RUS or LTPP | |||||
High Speed 1 (domestic) | 5,893 | 103.4% | 4,200 | 1,693 | 29% | 1,048 |
MML Long Distance | 5,800 | 200.0% | 2,900 | 2,900 | 50% | 3,335 |
Thameslink MML | 15,600 | 63.7% | 8,700 | 6,900 | 44% | 0 |
London King’s Cross | ||||||
Thameslink ECML | 27,200 | 113.3% | 13,700 | 13,500 | 50% | 6,800 |
Great Northern | ||||||
Hertford-Moorgate | ||||||
Welwyn Garden City-Moorgate | ||||||
ECML Long Distance | 5,300 | 108.2% | 4,900 | 400 | 8% | 1,135 |
London Liverpool Street | ||||||
West Anglia incl Main Line | 21,800 | 117.8% | 13,500 | 8,300 | 38% | 6,075 |
Great Eastern Main Line | 34,100 | 148.9% | 18,600 | 15,500 | 45% | 14,635 |
GE Inners | 24,900 | 106.9% | 10,900 | 14,000 | 56% | 5,095 |
Crossrail GE route | ||||||
Crossrail Abbey Wood route | 13,232 | 73.1% | 7,100 | 6,132 | 46% | 0 |
London Fenchurch Street | ||||||
All services | 23,800 | 118.4% | 14,900 | 8,900 | 37% | 6,715 |
To / Via London Bridge | ||||||
Terminating Sth. London (inners) | 12,900 | 97.0% | 9,800 | 3,100 | 24% | 1,595 |
Thameslink Sussex | 31,400 | 111.7% | 11,900 | 19,500 | 62% | 7,515 |
Terminating (fasts via E.Croydon) | ||||||
London Charing X/Waterloo East | 88,900 | 117.4% | 46,900 | 42,000 | 47% | 24,555 |
London Cannon Street | ||||||
Thameslink Kent | ||||||
London Victoria | ||||||
Kent routes | (inc above) | (inc above) | (inc above) | (inc above) | (inc above) | (inc above) |
Fast trains via East Croydon | 16,200 | 87.1% | 12,900 | 3,300 | 20% | 390 |
Stopping trains via Balham | 18,600 | 122.4% | 11,500 | 7,100 | 38% | 5,680 |
London Blackfriars | ||||||
Thameslink | 13,200 | 93.6% | 7,900 | 5,300 | 40% | 1,215 |
Terminating (all services) | ||||||
London Waterloo | ||||||
Windsor Lines (all services) | 18,300 | 94.8% | 9,000 | 9,300 | 51% | 1,895 |
Stopping trains via Wimbledon | 28,100 | 81.0% | 15,100 | 13,000 | 46% | 0 |
South West Main Line | 22,100 | 164.9% | 13,400 | 8,700 | 39% | 10,710 |
Main Orbital routes | ||||||
West London Line | 6,116 | 203.9% | 940 | 5,176 | 85% | 3,566 |
East London Line | 10,897 | 153.5% | 2,560 | 8,337 | 77% | 4,862 |
North London Line | 3,336 | 95.3% | 1,168 | 2,168 | 65% | 361 |
Commentary on 2031 and 2050+ forecast capacity gaps
We now see over a half-million commuters wanting to use rail in the busiest inbound peak hour. A 3 hour inbound peak volume would then be perhaps 1.15 million passengers, a throughput over 70% more than in 2010. These figures also ignore reverse-flow commuting, which is a growing phenomenon in London and the Home Counties.
Multiply that by roundly 1,100 to 1,250, and you see the annualised volumes rising to 1.26-1.43 billion, so that London’s National Rail network would on its own be handling nearly as many passengers as the whole of Britain’s main line railways do currently.
About half of the inbound passengers would be standing, including outer commuters, if they could get on the trains (and would be less likely to find space, any space, on the inners), in the unfortunate event of no new capacity being provided in the intervening decades.
Even with solutions to capacity gaps, the standee London commuter will be a more typical experience on National Rail, in future decades.
That’s enough numbers. What does this mean on the ground? The following 2031 commentary on capacity gaps and solutions is summarised from the LSE RUS. The 2050+ commentary on the further gaps foreseen in the LTPP is by this author.
2031 and 2050+ commentary on London main line capacity gaps and solutions
Route into | Potential interventions, other project comments. RUS comments for 2031 solutions. JRC comments for 2050+. |
---|---|
London Paddington | 2031: 5,800 long distance & outer suburban gap, HEX onto relief lines as Crossrail Express, allows 20 tph on fast lines. 2050+: Further 3,400 gap, numbers are pre-Heathrow Hub. Are the main options 6-tracking to Hayes, a new line, or a high capacity ‘digital railway’? (Also see SWML) Long distance passenger growth pressures may be under-estimated with attractiveness of commuting area, M4 congestion and GW electrification ‘sparks’ effect. |
London Marylebone | 2031: 1,200 gap = new tt, resignalling. 2050+: Further 3,600 gap, trains longer or other solution? There is potential for Chiltern-OOC and Chiltern-Heathrow. London 2050 mentions electrification. |
London Euston | 2031: 2,400 suburban gap, 8 tph via WCML-Crossrail. 2050+: Minor long distance gap (All 11-car WCML solves, plus several extra WCML slots). Further 4,500 suburban gap requires use of WCML fast slots. HS2 allows relief of these forecast WCML commuting pressures. |
London St Pancras | 2031: HS1 all 12-car. IEP, HS2 help with MML interCity capacity. 2050+: HS1 more paths, and to Hastings. MML gaps = 5-6 tph if average 450-500 pax/I’City train, feasible on MML. HS2 less likely to assist with 2060 capacity needs, if this is London outer commuting from Kettering etc. Is there a ‘digital railway’ solution for Thameslink outers standing? |
London King’s Cross | 2031: HS2 relieves ECML, high capacity trains for T’link ECML + Anglia. IEP for Kings Lynn [train spec changed now]. Higher tph on Moorgate line with 6-tracks Alexandra Palace-Finsbury Park. 2050+: Further 5,400 gap. The case for Crossrail 2 (CR2) starts here. Should CR2 trains run on GN? – might be good VfM and benefits, more line capacity if CR2 to Hertford. Welwyn viaduct/tunnel widening might be required for outer commuting, or ‘digital railway’ capacity gains. |
London Liverpool Street | 2031: WAML: +2tph began Dec.2011, 12-car services, Stratford shuttle by 2019. GEML: Crossrail 1, Bow-Stratford works, 12-car 26 tph early 2020s, 28 tph 2031. 2050+: Further 3,800 gap West Anglia, 9,500 GEML. New line(s) needed. WAML: Lea Valley 4-track + CR2. GEML: capacity gap if 800/900 per 12-cars = 11-12 tph. 8-track Liv.St. New GEML main line? Or WA 4-track via Stansted to Colchester? Crossrail 1 Gt.Eastern full. CR1 Abbey Wood full if to Ebbsfleet, see Fenchurch Street comments. More real tracks needed, not just ‘digital tracks’. |
London Fenchurch Street | 2031: Fenchurch St. full at 85% level, if all trains 12-car. 2050+: Further 6,800 gap. Another 8-9 tph. Points to new line also relieving Crossrail 1 branches. |
to/via London Bridge | 2031: Main capacity gain with Thameslink services (Kent now excluded), & all SE 12-car. [With no Thameslink Kent, will 2031 capacity be achieved?] Lengthening on Uckfield and Vic-Kent, and 12-car on Southern suburban. Clapham stops on Gatwick Express are also considered. 2050+: Forecast gap 27,300 extra. This is 30-34 tph, at 800/900 pax per train. Fewer tph if some 12-car inners and standees. Large-scale capacity shortfall from Kent and Sussex corridors, incl outer commuting. Overloads possible on SAZ links to Canary Wharf, Stratford, Old Oak Common. [Doesn’t help that Croydon isn’t included as a SAZ, to reduce inbound rail demand within London.] Can HS1 greater use and ATO etc on SE main lines solve this scale of problem? Might require at least one new line from outer London, possibly towards London Bridge and Canary or Stratford, plus potential for through 12-car services BML to Old Oak Common to connect with HS2, with re-organisation of Clapham Junction and East Croydon junctions. |
London Victoria | |
London Blackfriars | 2031: 900 gap causes RUS concern as frequency and platform capacities limit available solutions. RUS considers Overground-style trains. 2050+: Gap worsens, either high-density trains or platform lengthening or ‘digital railway’. |
London Waterloo | 2031: Re-use of Waterloo International & 10-car suburbans, addresses inner problems. SWML needs 5th track Waterloo-Surbiton, or Crossrail 2 relief, with full relief not guaranteed. 2050+: Further 5,000 gap, mainly SWML. 12-car Windsor lines, inners. The first 16-car commuter train, on SWML? SWML + GWML overload might point to new SW/GW main line, via Heathrow? |
Main Orbital Routes | 2031: 6,800 pax gap = 14 tph overall (JRC estimate). Longer trains needed. [Initial TfL project under way for 5-cars.] 8-car Southern trains on WLL also supported. 2050+: JRC demand projection is LSE RUS 2031 back to 2023 then x 20 years with PGS growth. Further gap 2,200, points to 6-8-car operation on all orbitals. |
These tables shows some stark consequences. Unless all London main line schemes proposed to 2031 are adopted in one form or other, the starting capacity in 2031 will be worse than expected, causing greater difficulties in succeeding years. That assumes HS2 and Crossrail 2 are built, along with a large range of 10-car and 12-car commuter operations. London 2050 population growth may make the 2031 gap a moving target. The forward gap to 2050+ is a call to action on many routes.
These PGS forecasts are not London 2050’s, but are in some ways easier to understand and more conventional than London 2050, because they are a straightforward Network Rail extrapolation of where it is thinks the shape of London and Home Counties travel to work is heading. London 2050 has largely restated the known Network Rail schemes, and then added further schemes to suit the potential spatial formats. Network Rail has also been busy thinking about other projects, so the London 2050 list includes some of those as well.
Has London ever had trains that have street run? (meaning trains that basically run on a road like a tram would but in most cases I believe the tracks pre-date the road which was built over it; commonly seen in America and formerly in Weymouth)
Anonymous
Grove Road in Deptford?
Grove STREET,sorry.
http://boroughphotos.org/lewisham/wp-content/uploads/2015/06/LEW_PH-93-18048-300×181.jpg
Anonymous
Almost certainly in the docks. And possibly the Surrey Iron Railway?
Anonyminibus
Oh,they were very smart indeed…they wouldn’t be seen dead without their shiny brass bell,lamp and footman waving a red flag and blowing a whistle…
Does the amazing Wisbech & Upwell tramway, count?
[ Just for swank value … I have done the track …. ]
@Greg
No it doesn’t – the question specifically said London, and Wisbech is not in London by any stretch of the imagination.
Recognising that it is very difficult to find the “right” place to talk about TfL taking on future franchises I’ve opted for here rather than the London Bridge Stn article.
A new TfL Board Paper has emerged setting out possible next steps on more TfL rail takeovers. Note there is nothing definitive as the key next steps require DfT and Mayoral sign off. Given the “argy bargy” at Mayor’s Question Time this morning between the Mayor and Gareth Bacon (Tory lead AM) you have to wonder quite what relations are like between Horseferry Rd and City Hall.
http://content.tfl.gov.uk/board-20160922-item07-suburban-rail-services.pdf
I’ve not read the paper yet and it’s 13 pages long so enjoy having a peruse.
WW – interesting paper. Cash not mentioned at all until the last section. Then when it does get a (brief) mention, the word ‘assumed’ is deployed.
My personal view – it’s not happening.
@ SFD – well I’ve read it now. There are slight hints of exasperation / borderline panic that time is running out and that in recent weeks the DfT hasn’t exactly been “responsive”. It was all going well with “Uncle Patrick” and now that new chap is there who hated the Mayor when he was an MP and opposition Justice spokesperson. Oops.
Interesting to see TfL’s “target list” confirmed as SE Inners, Southern inners, SWT inners and GN suburban from Moorgate. No obvious attempt to filch anything on the Thameslink core and unsurprisingly nothing on Chiltern / London Midland.
I see we have a new concept called “metroisation” being created which is pretty much the Overground recipe we all know and love with added removal of peak time freight workings to “other times”. Clearly the paper is pitched at informing a new TfL Board about the state of play and past achievements but it doesn’t read very “hopefully”. A board paper on TfL’s infrastructure “wish list” for CP6 is promised for later in the Autumn.
I hate to say it but I’m increasingly of the view that Mr Grayling isn’t playing ball and Mrs May won’t care enough to listen to any appeals. Having watched this morning’s inter play between the Mayor and Gareth Bacon where the latter sought to “explain” what franchises are, how they run and the need for “precise language” and for the Mayor to “not slag off franchisees” and to “use your influence with your friends the trade unions” one wonders who wrote the script. With the Mayor then referring to Mr Bacon as a “mouthpiece” you can see it is all going swimmingly. There was also a borderline tedious debate about the Mayor’s “top team of experts” who were going to be sent to “help out” on Southern’s woes. This also got very fractious over how many experts there were, what their day job was, how much they’d cost and what their names were. All a bit silly but clearly designed to make the Mayor look a bit clueless.
I hope I’m wrong that devolution isn’t slipping away but if South Eastern doesn’t go this time then it’s all over for devolution for this Mayoral term at least and the recriminations will not be nice. You don’t need to be a genius to see how the Mayor would present it nor how commuters in S London would react. In public the DfT will say little but some will no doubt delight in the wrecking of a key mayoral policy and retention of their control over those services.
The Tfl board report
1. Plenty of Ctrl C followed by Ctrl V
2. They seem unaware of SE services to Blackfriars especially those resuming in 2018, always worrying when they miss those minor details…
3. Someone is going to get a chunk of money for telling them they can’t afford it… (as the to do list is so much long and more expensive than West Anglia Overground start with 5x multiplier and then increase).
Or alternatively if they do take over SE metro the LO brand will get trashed and they won’t touch anything else.
4. DfT ain’t stupid and will want to cut subsidy to SE overall any kind of enhanced revenue collection will bring in the £s for TOCs and DfT.
5. They aren’t initial proposing any extra or replacement stock i.e. they aren’t looking to spend anything significant! Hence the average peak user would probably get a better deal with more metro stock from a conventional franchise arrangement between DfT and a TOC… (One potential bidder pricing up binning all the existing SE metro stock)
Most benefits are what could be regarded as largely to increase Off peak use and hence revenue when there is spare capacity.
6. Repeating the “it enables brownfield housing construction” mantra for the n’th time is little over done in such a short report.
Re WW,
I started to have the feeling a few weeks ago that there wouldn’t be too much new to show at the end of the term and virtually nothing in the pipeline for the next term.
The Mayor is already on thin ice in S London on the fare non freeze in S London so if this doesn’t happen then he is going to lose lots of votes.
The SoS is a long term Southern Metro user and also a former shadow SoS (who probably knew more than some of his opposite numbers at the time) so could easily be more credible than the Mayor.
Unless the mayor’s experts had a large amount of cash available and spent in in the past they aren’t going to solve Southern woes any more than GTR will. If the mayor doesn’t under stand this then…
WW
Your cynical analysis of the potential for childish political games at the expense of Londoners is, I’m afraid, all too plausible. Depressing, isn’t it?
ngh
So, Grayling actually knows something about the subject (?) – but OTOH will he make sensible suggestions, or will he follow his traditional right-wing dogma, as he did during his disastrous term as an Home Office/Prisons minister?
@ Ngh – a couple of comments as a counter point to what you’ve said.
1. I don’t think TfL have ever offered an instant peak time increase in capacity. They would be foolhardy to do so with the stretched South Eastern fleet and no clear idea how a franchise split would affect the fleet.
2. The “metroisation” section does talk about new rolling stock with better performance attributes helping to raise capacity and / or frequencies. To be honest that seems fair enough and fits with the general Overground way of doing things. I would expect TfL to order new stock – possibly large quantities of it to give more peak capacity per train where feasible and to allow off peaks to be bolstered too. It strikes me South Eastern could take a lot more off peak traffic if the service was more attractive.
3. South Eastern have lots of ticket gates but they’re left open or locked away in sealed enclosures a lot of the time from my albeit limited use of South Eastern. The magic cure is to actually fund adequate staffing levels so the gates remain in service all day. We know TfL would do this. We can’t yet know what the DfT would specify on this.
4. I think it’s a tad harsh to criticise the “develop brownfield sites” point. This is the vogue for City Hall *and* Network Rail. It plays to the electorate’s demand for much more housing, it makes sense to have better transport to support mobility from new housing and it’s in the broad sweep of government policy around more housing. It’s also part of the funding plan for Network Rail – I recall Sir Peter Hendy waxing lyrical about the potential that NR has to help build more houses.
Yes the paper is a lot of “cut and paste”. Yes it says very little since about developments since May – presumably because there haven’t been any! The brutal truth is that the power sits with Mr Grayling and it’s his final say that determines where we go next. However I don’t think we should be shocked that the new TfL Board is being given a paper on what is a key mayoral policy and which has a major milestone approaching. To not provide such a paper would have been the bigger shock.
@ Greg – the prospects don’t look great. That seems to be the emerging consensus view. We only have a few more weeks to wait to see what happens and who knows what might go on in those few weeks. We’ve seen plenty of shocks in recent weeks.
@WW, ngh, Greg
… the prospects don’t look great for more TfL rail takeovers
Clearly the SoS believes that the political price for blocking TfL and Sadiq will be low.
So, what could change this calculation? A social media campaign?
@answer=42: Local newspapers….
Chris Grayling (at yesterday’s Transport Questions in the House of Commons): “My policy and the Government’s policy is that devolution should happen where it will make a difference, not simply for its own sake. I need to see the Mayor’s proposals about how he thinks he can enhance services in London—I am looking forward to seeing them—before I consider any changes.”
@anon 14:28
the sense of the informed comments by WW and ngh is that Grayling is preventing TfL from submitting a well-developed proposal through DfT non-cooperation. On the other hand, he has deliberately left the door open, so there is an opportunity to push.
@ Anon – thanks for that update. Excuse me while I sit here being puzzled. I assume that TfL and the Department have been in discussions about a wide range of things on devolution for many, many months. We would not have got to the point of the “prospectus” being agreed if there had been no dialogue. I trust the SoS is not saying that no one in his department has not sat down with him and taken him through the background on such a key policy for London? I would assume that background includes info on what has been achieved to date across a wide range of measures / attributes plus the general policy thrust for the future. I’d also expect someone in the DfT to have been engaged with people in TfL about the service groupings that could transfer to TfL. If they haven’t been then there’s zero prospect of a last minute dash to rewrite the procurement paperwork and everything that supports it for the retendering of South Eastern. I also assume that if Mr Grayling had said “could City Hall and TfL send some people over to brief me on their devolution plans?” that they’d have been there “tout de suite”. Or is this a case of “I’m the boss, I wait for others to request a meeting with me.”? Can’t have the Mayor thinking he’s of equal status to a Secretary of State now can we?
According to the DfT’s rail franchise schedule the pre qualification passport application date for South Eastern was in August and the Expressions of Interest are due in November. Someone must have defined what bidders are being asked to pre-qualify for and what to express interest in. I guess they may have held back and said “these bits might be devolved at some point” but that has to be firmed up pretty quickly and TfL have to be “ready to go” with their own procurement imminently if the intention is to devolve services on a common date in late 2018 (at the very, very latest). June 2018 is the current end date of the South Eastern franchise but it can be extended by 28 weeks. Even though the SE ITT is due out in April 2017 you don’t turn such complex documents out in a matter of weeks. It takes months and months of work, checking, rework etc before it gets to the point of passing through whatever internal sign offs there will be on the government side. Ditto if TfL were to procure the inner suburban services. They must have been working on the details for months by now.
If we take Mr Garyling’s statement at face value then I’m not impressed with what has / has not been going on. However he’s a politician so I don’t take anything he says at face value. 😉
WW – In answer to a question on BML2 he said he was “very interested in this as a proposal” so…
I wonder if there’s room for programme/alliance/steering board (call it what you may) involving DfT and TfL with managers of the new SE franchise sitting in? This would be along the lines of the Board that has been set up to oversee Northern? This could be done much more easily than devolution but could allow robust plans to be developed for the following franchise.
WW
C Grayling’s constituency is Epsom & Ewell.
Therefore he must (surely?) be aware of the nature of the problems affecting rail travellers all across S & SE London?
It does seem as though either DfT are taking advantage, in their turf war with “London” …[OVERTLY PARTY-POLITICAL OBSERVATIONS SNIPPED. MALCOLM] …
Of course I could be wrong, but like you, my cynicism index number is rising.
I trust that people here are benefiting from the spoof “Grayling and Sadiq” conversations being broadcast by one John Bull (@garius) on Twitter. As Malcolm likes to remind us periodically, ‘other fora are available’.
Graham H is much better qualified to opine than me, but there are occasions when a little light murmuring (suitably targeted) can open up things which are unaffected by shouting in public (or on social media, whatever they are)
@Old Buccaneer – that certainly used to be the case, although I fear there has been a trend over the last decade or so to think that if you fail to convince or are proved wrong, it’s because you failed to use a big enough megaphone (bullhorn for our transatlantic colleagues), not because you were actually, err, wrong. Talk about the sleep of Reason.
@Greg
Just because the SofS has an Epsom constituency while he may well be aware of the problems, it doesn’t mean that he is signed up to – or even accepts – the type of solutions that many of the readers of this piece will accept as realistic. Were he to be of the more dogmatic type (such as those in charge at the CMA) he may simply believe that more and purer competition is the right answer, for example. While it is encouraging that the Prime Minister has expressed her support for evidence based policy making – something which had been dropped by the previous PM) – the actuality of other decisions, such as on grammar schools, suggests that faith based policy making is still in the ascendent.
@ Anon 1501 – Erk! We know what that answer means.
@ 100&30 – I think the wearisome users of South Eastern’s inner suburban services might respond with a torrent of expletives if faced with the prospect of another franchise term not under TfL control. The irony is, of course, that if they were really really bolshy, like C2C commuters have been trained by experience to be, then improvements would have been forthcoming by now. The other problem is that the outer SE London seats are all safe Tory seats so the MPs won’t do anything to upset the DfT esp as two of them are Ministers (in other departments). You’ll also note the lack of any great noise from a Mr Barwell of Croydon about Southern – 3 tweets over many months. I can’t see a “board” consisting of members with little actual power to do anything being sensible. Oversight is all very well but if the DfT take no notice of what’s said then all you’ve got is an annoyed “board”. It’s perfectly clear from years and years of experience that the DfT aren’t that bothered about South Eastern other than getting a lot more money out of the franchise and shoving up fares that were historically lower than elsewhere. Not such else of any great import has happened. That London Bridge might eventually bring about a smoother run through that area for South Eastern pax is incidental to the main objectives for Thameslink.
@ OB 2249 – “Benefitting” might be seriously stretching my thoughts about Mr B’s “Sadiq and Chris” tweets. I thought my imagination was seriously “odd” at times but it hasn’t got anything on Mr B’s.
WW…Your points very well made.
However, regardless of who is in charge, significant improvement will require a healthy dose of money to do the works (infrastructure and rolling stock) and, practically, there are only two source of money (I know you this). TfL is not flush, and I’m sure the customers won’t be too keen to stump up more. Thus there needs to be very strong support from the DfT to provide the dosh.
@ Greg – I am sure he is aware but being SoS doesn’t mean you magically wave a wand and fix things for your own constituents to the possible detriment of others. As others have said he may well have completely different views about the dispute, who is responsible and what the “right” answer is. If passengers’ disruption is the “collateral damage” in the fight to achieve other objectives then that may be considered “worthwhile” in the short term.
As for other things I’d like to say they must wait for PoP’s analysis of the TSGN timetable consultation or else machetes will be wielded.